Corriemoillie 132/33kV: grid connection queue

Corriemoillie 132/33kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 200 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2033 to 31 Oct 2033.

1project in the queue
200 MWwaiting to connect
48 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Isenau FourIsenau Energy Storage Resources Four LimitedBattery storage20031 Oct 2033Low31 Oct 2033Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Loch Glascarnoch PrimarySSEN Distribution5.6 km0 MW0.6 MW
Grudie Bridge GSPSSEN Distribution5.8 km
Garbat Forest PrimarySSEN Distribution7.0 km0 MW0.1 MW
Comrie PrimarySSEN Distribution13.1 km0 MW0 MW
Orrin GSPSSEN Distribution15.6 km
Marybank PrimarySSEN Distribution18.1 km0 MW0 MW

Thinking of connecting near Corriemoillie 132/33kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.