Loch Luichart Extension II: grid connection queue
Loch Luichart Extension II Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 36 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 31 Oct 2024 to 31 Oct 2024.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Loch Luichart Extension II | BLUEBELL WIND FARM LIMITED | Onshore wind | 36 | 31 Oct 2024 | n/a | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Loch Glascarnoch Primary | SSEN Distribution | 4.3 km | 0 MW | 0.6 MW |
| Grudie Bridge GSP | SSEN Distribution | 5.3 km | ||
| Garbat Forest Primary | SSEN Distribution | 9.9 km | 0 MW | 0.1 MW |
| Comrie Primary | SSEN Distribution | 15.3 km | 0 MW | 0 MW |
| Orrin GSP | SSEN Distribution | 17.9 km |
Thinking of connecting near Loch Luichart Extension II?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Corriemoillie 132kV: 200 MW waiting
- Corriemoillie 132/33kV: 200 MW waiting
- Corriemoillie 2 400/132kV: 82 MW waiting
- Carn Fearna Wind Farm 132/33kV: 85 MW waiting
- Fairburn Extension 132/33kV: 90 MW waiting