Carn Fearna Wind Farm 132/33kV: grid connection queue

Carn Fearna Wind Farm 132/33kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 85 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 30 Jun 2030 to 30 Jun 2030.

1project in the queue
85 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
85 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Carn Fearna Wind FarmCarn Fearna Wind Farm LimitedOnshore wind8530 Jun 2030High16 May 2032Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Comrie PrimarySSEN Distribution5.6 km0 MW0 MW
Garbat Forest PrimarySSEN Distribution6.9 km0 MW0.1 MW
Orrin GSPSSEN Distribution7.9 km
Grudie Bridge GSPSSEN Distribution8.6 km
Marybank PrimarySSEN Distribution10.3 km0 MW0 MW
Loch Glascarnoch PrimarySSEN Distribution13.3 km0 MW0.6 MW

Thinking of connecting near Carn Fearna Wind Farm 132/33kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.