IMW01 OFFSHORE 275/66KV OFFSHORE SUBSTATION: grid connection queue
IMW01 OFFSHORE 275/66KV OFFSHORE SUBSTATION · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 1,320 MW is waiting to connect here (largest by capacity: offshore wind). Contracted dates run from 30 Sep 2037 to 30 Sep 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Isle of Man Offshore Wind Farm | Mooir Vannin Offshore Wind Farm Limited | Offshore wind | 1,320 | 30 Sep 2037 | Low | 30 Sep 2037 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 1 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 20 Oct 2026 | Isle of Man Offshore Wind Farm | 30 Jul 2037 | 30 Sep 2037 | +2 months |
| 13 Oct 2026 | Isle of Man Offshore Wind Farm | 30 Oct 2037 | 30 Jul 2037 | -3 months |
Thinking of connecting near IMW01 OFFSHORE 275/66KV OFFSHORE SUBSTATION?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.