An Suidhe 275/33kV: grid connection queue
An Suidhe 275/33kV · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 105 MW is waiting to connect here (largest by capacity: onshore wind + storage). Contracted dates run from 1 Nov 2029 to 1 Nov 2029.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Eredine Wind Farm | RWE Renewables UK Onshore Wind Limited | Onshore wind + storage | 105 | 1 Nov 2029 | High | 18 Sep 2031 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Kingussie Primary | SSEN Distribution | 8.9 km | 0 MW | 0 MW |
| Aviemore Primary | SSEN Distribution | 9.5 km | 0 MW | 1.3 MW |
| Boat of Garten GSP | SSEN Distribution | 18.9 km | ||
| Boat of Garten Primary | SSEN Distribution | 18.9 km | 0 MW | 7.2 MW |
Thinking of connecting near An Suidhe 275/33kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Aberarder Extension Wind Farm 132/33kV: 138 MW waiting
- Aberarder Wind Farm 132/33kV: 50 MW waiting
- Tomatin 132kV Substation Extension: 91 MW waiting
- Clune 132/33 kV: 187 MW waiting
- Lynemore Windfarm 132kV: 84 MW waiting