Sundhope 132kV: grid connection queue

Sundhope 132kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 180 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 30 May 2033 to 30 May 2033.

1project in the queue
180 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Sundhope Wind FarmBlack Knowe Energy LimitedOnshore wind18030 May 2033Low30 May 2033Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Thinking of connecting near Sundhope 132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.