Market Harborough 400kV: grid connection queue

Market Harborough 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

4 projects with 2,060 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 31 Oct 2031 to 28 Oct 2033.

4projects in the queue
2,060 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Braybrooke Solar and Battery ConnectionIrena BESS LIMITEDSolar + storage50031 Oct 2031Medium31 Oct 2031Scoping1
BraybrookeSSE DE SOLAR HOLDCO LIMITEDBattery storage60031 Jul 2032Low31 Jul 2032Scoping1
Market Harborough GEC (Ethos Green)MARKET HARBOROUGH GREEN ENERGY CENTRE LTDSolar + storage56031 Oct 2032Low31 Oct 2032Awaiting Consents1
ER MKH EnergyER PROJECT DEVELOPMENT CO LIMITEDSolar + storage40028 Oct 2033Low28 Oct 2033Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Thinking of connecting near Market Harborough 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points