Enderby 400kV: grid connection queue
Enderby 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
3 projects with 2,082 MW are waiting to connect here (largest by capacity: solar + storage, mixed and other). Contracted dates run from 31 Aug 2028 to 30 Oct 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Enderby Tertiary | CLUMP FARM SOLAR LIMITED | Solar | 57 | 31 Aug 2028 | High | 15 Sep 2030 | Consents Approved | 2 |
| Enderby Green Energy Centre | ENDERBY BESS LIMITED | Solar + storage | 1,025 | 30 Oct 2028 | High | 30 Oct 2030 | Awaiting Consents | none |
| Rugby High Impact Green Energy Hub (HIGEH) 1 | TELIS ENERGY UK LIMITED | Mixed and other | 1,000 | 30 Oct 2037 | Low | 30 Oct 2037 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 4 times: 3 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 3 Nov 2026 | Rugby High Impact Green Energy Hub (HIGEH) 1 | 31 Oct 2033 | 30 Oct 2037 | +48 months |
| 20 Oct 2026 | Rugby High Impact Green Energy Hub (HIGEH) 1 | 30 Oct 2037 | 31 Oct 2033 | -48 months |
| 13 Oct 2026 | Rugby High Impact Green Energy Hub (HIGEH) 1 | 31 Oct 2034 | 30 Oct 2037 | +36 months |
| 13 Oct 2026 | Enderby Tertiary | 1 Aug 2027 | 31 Aug 2028 | +13 months |
Thinking of connecting near Enderby 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Earl Shilton 275kV: 500 MW waiting
- Earl Shilton 400kV: 250 MW waiting
- Trent Valley South Connection Node A 400k: 400 MW waiting
- Ratcliffe: 130 MW waiting
- Ratcliffe-On-Soar 400kV: 590 MW waiting