Dunan Hill 400kV substation: grid connection queue

Dunan Hill 400kV substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 250 MW is waiting to connect here (largest by capacity: onshore wind + storage). Contracted dates run from 31 Oct 2035 to 31 Oct 2035.

1project in the queue
250 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
1date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Dunan HillPERIGUS ENERGY UK LIMITEDOnshore wind + storage25031 Oct 2035Low31 Oct 2035Scoping1

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 0 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
20 Oct 2026Dunan Hill1 Nov 203631 Oct 2035-12 months

Thinking of connecting near Dunan Hill 400kV substation?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.