Connagill 275kV: grid connection queue
Connagill 275kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
2 projects with 190 MW are waiting to connect here (largest by capacity: onshore wind + storage, onshore wind). Contracted dates run from 29 Oct 2029 to 31 Oct 2032.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Kirkton Wind Farm | Kirkton Wind Farm Limited | Onshore wind | 60 | 29 Oct 2029 | High | 15 Sep 2031 | Awaiting Consents | 1 |
| Altnabreac Windfarm | ALTNABREAC WIND FARM LIMITED | Onshore wind + storage | 130 | 31 Oct 2032 | Low | 31 Oct 2032 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 13 Oct 2026 | Kirkton Wind Farm | 31 Oct 2028 | 31 Oct 2029 | +12 months |
Thinking of connecting near Connagill 275kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.