Warley 132kV: grid connection queue
Warley 132kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 480 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2036 to 31 Oct 2036.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| St. Marys Lane - Upminster BESS | Bluestone Energy Ltd | Battery storage | 240 | 31 Oct 2036 | Low | 31 Oct 2036 | Scoping | 1 |
| Upminster Warley 3 | Bluestone Energy Ltd | Battery storage | 240 | 31 Oct 2036 | Low | 31 Oct 2036 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Brentwood Primary 11kV | UK Power Networks | 1.7 km | 24 MW | 8.6 MW |
| High St Primary 11kV | UK Power Networks | 2.4 km | 32 MW | 2.2 MW |
| West Horndon Primary 11kV | UK Power Networks | 4.2 km | 4 MW | 0.8 MW |
| Harold Wood Primary 11kV | UK Power Networks | 4.4 km | 21 MW | 9.6 MW |
| Cranham Primary 11kV | UK Power Networks | 4.5 km | 22 MW | 6.8 MW |
| Straight Rd Primary 11kV | UK Power Networks | 6.1 km | 22 MW | 3.6 MW |
Thinking of connecting near Warley 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Warley 275kV: 1,231 MW waiting
- London North East Connection Node A 132kv: 200 MW waiting
- Littlebrook 132kV: 550 MW waiting
- Littlebrook 400kV: 57 MW waiting
- Barking West: 100 MW waiting