Hawick: grid connection queue
Hawick GSP · SP Transmission (southern Scotland) · register of 26 November 2026
2 projects with 143 MW are waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 2 Aug 2023 to 30 Oct 2029.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Pines Burn Wind Farm | PINES BURN WIND FARM LLP | Onshore wind | 50 | 2 Aug 2023 | n/a | Consents Approved | none | |
| Millmoor Rig Wind Farm | ESB ASSET DEVELOPMENT UK LIMITED | Onshore wind | 93 | 30 Oct 2029 | High | 16 Sep 2031 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Denholm | SP Energy Networks | 4.8 km | 3 MW | 6 MW |
| Commercial Road | SP Energy Networks | 7.3 km | 1.6 MW | |
| Deans Close | SP Energy Networks | 10.9 km | 3 MW | 4.2 MW |
| St. Boswells | SP Energy Networks | 17.7 km | 8.7 MW | 2.6 MW |
| Selkirk | SP Energy Networks | 19.3 km | 11 MW | 4.5 MW |
Thinking of connecting near Hawick?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Hawick 132kV: 264 MW waiting
- Mid Hill 132kV: 228 MW waiting
- Teviot 400/132kV: 808 MW waiting
- Galashiels 132/33kV: 73 MW waiting
- Borders Connection Node A 400kV: 200 MW waiting