Hawick 132kV: grid connection queue

Hawick 132kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026

2 projects with 264 MW are waiting to connect here (largest by capacity: onshore wind + storage, onshore wind). Contracted dates run from 31 Oct 2033 to 3 Jul 2034.

2projects in the queue
264 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Brown Rig Wind FarmSSE Renewables Services (UK) LimitedOnshore wind11431 Oct 2033Low31 Oct 2033Scoping1
Woodland RidgeCubico UK Development LimitedOnshore wind + storage1503 Jul 2034Low3 Jul 2034Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
DenholmSP Energy Networks4.8 km3 MW6 MW
Commercial RoadSP Energy Networks7.3 km1.6 MW
Deans CloseSP Energy Networks10.9 km3 MW4.2 MW
St. BoswellsSP Energy Networks17.7 km8.7 MW2.6 MW
SelkirkSP Energy Networks19.3 km11 MW4.5 MW

Thinking of connecting near Hawick 132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points