Mid Hill 132kV: grid connection queue
Mid Hill 132kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 228 MW is waiting to connect here (largest by capacity: onshore wind + storage). Contracted dates run from 30 Oct 2034 to 30 Oct 2034.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Mid Hill | Invenergy Development UK Ltd | Onshore wind + storage | 228 | 30 Oct 2034 | Low | 30 Oct 2034 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Commercial Road | SP Energy Networks | 10.4 km | 1.6 MW | |
| Denholm | SP Energy Networks | 17.6 km | 3 MW | 6 MW |
Thinking of connecting near Mid Hill 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Teviot 400/132kV: 808 MW waiting
- Hawick 132kV: 264 MW waiting
- Hawick: 143 MW waiting
- Galashiels 132/33kV: 73 MW waiting
- Hopsrig Collector 132/33kV: 52 MW waiting