Mid Hill 132kV: grid connection queue

Mid Hill 132kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 228 MW is waiting to connect here (largest by capacity: onshore wind + storage). Contracted dates run from 30 Oct 2034 to 30 Oct 2034.

1project in the queue
228 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Mid HillInvenergy Development UK LtdOnshore wind + storage22830 Oct 2034Low30 Oct 2034Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Commercial RoadSP Energy Networks10.4 km1.6 MW
DenholmSP Energy Networks17.6 km3 MW6 MW

Thinking of connecting near Mid Hill 132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points