Hopsrig Collector 132/33kV: grid connection queue

Hopsrig Collector 132/33kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026

2 projects with 52 MW are waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 15 Dec 2026 to 31 Oct 2029.

2projects in the queue
52 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
52 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Dealanach WLC WFDEALANACH LIMITEDOnshore wind1215 Dec 2026High11 Feb 2029Scopingnone
Hareshaw Rig Wind FarmHARESHAW RIG WF LIMITEDOnshore wind4031 Oct 2029High17 Sep 2031Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
LangholmSP Energy Networks8.5 km-0.5 MW20 MW
MiddlebieSP Energy Networks14.4 km-1.3 MW-0.1 MW
LockerbieSP Energy Networks16.9 km27 MW8.6 MW
KirkbankSP Energy Networks18.9 km10 MW5.3 MW

Thinking of connecting near Hopsrig Collector 132/33kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.