Appin Wind Farm 132kV: grid connection queue
Appin Wind Farm 132kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 66 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 31 Oct 2031 to 31 Oct 2031.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Appin Wind Farm | Appin Wind Farm Limited | Onshore wind | 66 | 31 Oct 2031 | High | 16 Sep 2033 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Langholm | SP Energy Networks | 0.6 km | -0.5 MW | 20 MW |
| Newcastleton | SP Energy Networks | 12.2 km | 3.9 MW | |
| Primary substation 609612 | Electricity North West | 14.1 km | 2.4 MW | 0 MW |
| Middlebie | SP Energy Networks | 17.0 km | -1.3 MW | -0.1 MW |
| Bulk supply point 609621_11/33KV - No Heatmap Values | Electricity North West | 18.3 km | ||
| Gretna | SP Energy Networks | 18.4 km | 26 MW | 16 MW |
Thinking of connecting near Appin Wind Farm 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Hopsrig Collector: 84 MW waiting
- Callisterhall 132kV: 46 MW waiting
- Hopsrig Collector 132/33kV: 52 MW waiting
- Chapelcross 132/33kV: 151 MW waiting
- Wyseby Hill Energy Farm 400kV: 750 MW waiting