Hopsrig Collector: grid connection queue

Hopsrig Collector Substation · SP Transmission (southern Scotland) · register of 26 November 2026

2 projects with 84 MW are waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 31 Oct 2027 to 31 Oct 2027.

2projects in the queue
84 MWwaiting to connect
0 MWalready connected
84 MWholding Gate 2
0date moves since 2 Jun 2026
84 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Hopsrig Wind FarmHOPSRIG WIND FARM LIMITEDOnshore wind4831 Oct 2027High28 Dec 2029Consents Approved2
Loganhead WindfarmLOGANHEAD WF LIMITEDOnshore wind3631 Oct 2027High28 Dec 2029Consents Approved2

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
LangholmSP Energy Networks7.5 km-0.5 MW20 MW
MiddlebieSP Energy Networks14.1 km-1.3 MW-0.1 MW
LockerbieSP Energy Networks17.2 km27 MW8.6 MW
NewcastletonSP Energy Networks19.3 km3.9 MW
KirkbankSP Energy Networks19.7 km10 MW5.3 MW

Thinking of connecting near Hopsrig Collector?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.