Hopsrig Collector: grid connection queue
Hopsrig Collector Substation · SP Transmission (southern Scotland) · register of 26 November 2026
2 projects with 84 MW are waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 31 Oct 2027 to 31 Oct 2027.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Hopsrig Wind Farm | HOPSRIG WIND FARM LIMITED | Onshore wind | 48 | 31 Oct 2027 | High | 28 Dec 2029 | Consents Approved | 2 |
| Loganhead Windfarm | LOGANHEAD WF LIMITED | Onshore wind | 36 | 31 Oct 2027 | High | 28 Dec 2029 | Consents Approved | 2 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Langholm | SP Energy Networks | 7.5 km | -0.5 MW | 20 MW |
| Middlebie | SP Energy Networks | 14.1 km | -1.3 MW | -0.1 MW |
| Lockerbie | SP Energy Networks | 17.2 km | 27 MW | 8.6 MW |
| Newcastleton | SP Energy Networks | 19.3 km | 3.9 MW | |
| Kirkbank | SP Energy Networks | 19.7 km | 10 MW | 5.3 MW |
Thinking of connecting near Hopsrig Collector?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Hopsrig Collector 132/33kV: 52 MW waiting
- Callisterhall 132kV: 46 MW waiting
- Chapelcross 132/33kV: 151 MW waiting
- Appin Wind Farm 132kV: 66 MW waiting
- Wyseby Hill Energy Farm 400kV: 750 MW waiting