Teeside Connection Node A 400kV: grid connection queue
Teeside Connection Node A 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 1,240 MW are waiting to connect here (largest by capacity: battery storage, solar + storage). Contracted dates run from 31 Oct 2033 to 31 Oct 2035.
2projects in the queue
1,240 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Lackenby PV & BESS Station | IB VOGT UK LTD | Solar + storage | 240 | 31 Oct 2033 | Low | 31 Oct 2033 | Scoping | 1 |
| NatPower Teesside Green Energy Park | Old Rides Energy Storage Limited | Battery storage | 1,000 | 31 Oct 2035 | Low | 31 Oct 2035 | Consents Approved | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Teeside Connection Node A 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Teeside Connection Node 2 C 132/400kV: 2,400 MW waiting
- Teeside Connection Node A 132kV: 228 MW waiting
- Saltholme 275kV: 200 MW waiting
- Tod Point 275kV: 860 MW waiting
- Lackenby 400kV: 1,800 MW waiting