Benzene

Teeside Connection Node A 400kV: grid connection queue

Teeside Connection Node A 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

2 projects with 1,240 MW are waiting to connect here (largest by capacity: battery storage, solar + storage). Contracted dates run from 31 Oct 2033 to 31 Oct 2035.

2projects in the queue
1,240 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Lackenby PV & BESS StationIB VOGT UK LTDSolar + storage24031 Oct 2033Low31 Oct 2033Scoping1
NatPower Teesside Green Energy ParkOld Rides Energy Storage LimitedBattery storage1,00031 Oct 2035Low31 Oct 2035Consents Approvednone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Thinking of connecting near Teeside Connection Node A 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points