Teeside Connection Node 2 C 132/400kV: grid connection queue

Teeside Connection Node 2 C 132/400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 2,400 MW is waiting to connect here (largest by capacity: gas and thermal). Contracted dates run from 30 Oct 2035 to 30 Oct 2035.

1project in the queue
2,400 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Bute Hydrogen Project 4HALDANE ENERGY PROJECT 4 LIMITEDGas and thermal2,40030 Oct 2035Low30 Oct 2035Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Thinking of connecting near Teeside Connection Node 2 C 132/400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points