Teeside Connection Node 2 C 132/400kV: grid connection queue
Teeside Connection Node 2 C 132/400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 2,400 MW is waiting to connect here (largest by capacity: gas and thermal). Contracted dates run from 30 Oct 2035 to 30 Oct 2035.
1project in the queue
2,400 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Bute Hydrogen Project 4 | HALDANE ENERGY PROJECT 4 LIMITED | Gas and thermal | 2,400 | 30 Oct 2035 | Low | 30 Oct 2035 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Teeside Connection Node 2 C 132/400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Teeside Connection Node A 132kV: 228 MW waiting
- Saltholme 275kV: 200 MW waiting
- Tod Point 275kV: 860 MW waiting
- Teeside Connection Node A 400kV: 1,240 MW waiting
- Teeside Connection Node B: 3,600 MW waiting