Tod Point 275kV: grid connection queue

Tod Point 275kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 860 MW is waiting to connect here (largest by capacity: gas and thermal). Contracted dates run from 30 Jul 2027 to 30 Jul 2027.

1project in the queue
860 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
860 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Net Zero Teesside Power ProjectNET ZERO TEESSIDE POWER LIMITEDGas and thermal86030 Jul 2027High13 Mar 2030Consents Approvednone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Thinking of connecting near Tod Point 275kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points