Fife Grid Services Facility 275kV: grid connection queue
Fife Grid Services Facility 275kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026
2 projects with 400 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 15 Dec 2028 to 15 Dec 2028.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Kincardine Battery Storage Facility | KINCARDINE GRID 1 LTD | Battery storage | 200 | 15 Dec 2028 | Medium | 15 Dec 2028 | Consents Approved | 2 |
| Kincardine Energy Storage Facility | KINCARDINE GRID 1 LTD | Battery storage | 200 | 15 Dec 2028 | Medium | 15 Dec 2028 | Consents Approved | 2 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 2 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 9 Jun 2026 | Kincardine Battery Storage Facility | 31 Mar 2026 | 15 Dec 2028 | +32 months |
| 9 Jun 2026 | Kincardine Energy Storage Facility | 30 Jul 2027 | 15 Dec 2028 | +17 months |
Thinking of connecting near Fife Grid Services Facility 275kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.