Fife Grid Services Facility 275kV: grid connection queue

Fife Grid Services Facility 275kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026

2 projects with 400 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 15 Dec 2028 to 15 Dec 2028.

2projects in the queue
400 MWwaiting to connect
0 MWalready connected
400 MWholding Gate 2
2date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Kincardine Battery Storage FacilityKINCARDINE GRID 1 LTDBattery storage20015 Dec 2028Medium15 Dec 2028Consents Approved2
Kincardine Energy Storage FacilityKINCARDINE GRID 1 LTDBattery storage20015 Dec 2028Medium15 Dec 2028Consents Approved2

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 2 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
9 Jun 2026Kincardine Battery Storage Facility31 Mar 202615 Dec 2028+32 months
9 Jun 2026Kincardine Energy Storage Facility30 Jul 202715 Dec 2028+17 months

Thinking of connecting near Fife Grid Services Facility 275kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.