Stracathro BESS 275kV: grid connection queue

Stracathro BESS 275kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 249 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Jun 2032 to 30 Jun 2032.

1project in the queue
249 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Stracathro BESSOpdenergy UK 8 LimitedBattery storage24930 Jun 2032Low30 Jun 2032Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Inchbare PrimarySSEN Distribution2.7 km0 MW1.6 MW
Brechin PrimarySSEN Distribution4.1 km0 MW3.8 MW
Logie Pert PrimarySSEN Distribution5.3 km0 MW3.6 MW
Bridge of Dun GSPSSEN Distribution5.8 km
Bridge of Dun PrimarySSEN Distribution5.8 km0 MW1.5 MW
Edzell PrimarySSEN Distribution7.1 km0 MW0 MW

Thinking of connecting near Stracathro BESS 275kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points