Brechin 400/275 kV: grid connection queue
Brechin 400/275 kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 1,320 MW is waiting to connect here (largest by capacity: offshore wind). Contracted dates run from 31 Oct 2033 to 31 Oct 2033.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Ossian 1 Offshore Wind Farm | Ossian Offshore Wind Farm Limited | Offshore wind | 1,320 | 31 Oct 2033 | Low | 31 Oct 2033 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Brechin Primary | SSEN Distribution | 1.4 km | 0 MW | 3.8 MW |
| Inchbare Primary | SSEN Distribution | 5.3 km | 0 MW | 1.6 MW |
| Bridge of Dun GSP | SSEN Distribution | 6.4 km | ||
| Bridge of Dun Primary | SSEN Distribution | 6.4 km | 0 MW | 1.5 MW |
| Logie Pert Primary | SSEN Distribution | 9.1 km | 0 MW | 3.6 MW |
| Friockheim Primary | SSEN Distribution | 10.9 km | 0 MW | 2.5 MW |
Thinking of connecting near Brechin 400/275 kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Stracathro BESS 275kV: 249 MW waiting
- Bridge of Dun: 50 MW waiting
- Arbroath: 135 MW waiting
- Arbroath 2 132/33kV GSP: 50 MW waiting
- Lunanhead 2: 50 MW waiting