Arbroath 2 132/33kV GSP Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 50 MW is waiting to connect here (largest by capacity: solar). Contracted dates run from 31 Oct 2032 to 31 Oct 2032.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Fauldielaw | CAIRN DUHIE ENERGY LIMITED | Solar | 50 | 31 Oct 2032 | Low | 31 Oct 2032 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Arbroath GSP | SSEN Distribution | 3.0 km | ||
| Elliot Depot Primary | SSEN Distribution | 3.5 km | 0 MW | 0 MW |
| Redford Primary | SSEN Distribution | 3.9 km | 0 MW | 0 MW |
| Charles Avenue Primary | SSEN Distribution | 4.0 km | 0 MW | 0 MW |
| Hume Street Primary | SSEN Distribution | 5.0 km | 0 MW | 0 MW |
| Carnoustie Primary | SSEN Distribution | 7.3 km | 0 MW | 0 MW |
Thinking of connecting near Arbroath 2 132/33kV GSP?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Arbroath: 135 MW waiting
- Milton of Craigie: 68 MW waiting
- Tealing 400kV: 1,900 MW waiting
- Tealing 132kV: 700 MW waiting
- Tealing IDNO 132/33kV: 80 MW waiting