Bridge of Dun: grid connection queue
Bridge of Dun GSP · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 50 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Jun 2032 to 30 Jun 2032.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Dunmill Energy Storage | Dunmill Energy Storage Limited | Battery storage | 50 | 30 Jun 2032 | Low | 30 Jun 2032 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Inchbare Primary | SSEN Distribution | 7.1 km | 0 MW | 1.6 MW |
| Edzell Primary | SSEN Distribution | 7.8 km | 0 MW | 0 MW |
| Brechin Primary | SSEN Distribution | 12.0 km | 0 MW | 3.8 MW |
| Logie Pert Primary | SSEN Distribution | 13.5 km | 0 MW | 3.6 MW |
| Laurencekirk Primary | SSEN Distribution | 15.2 km | 0 MW | 0 MW |
| Bridge of Dun GSP | SSEN Distribution | 15.5 km |
Thinking of connecting near Bridge of Dun?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Stracathro BESS 275kV: 249 MW waiting
- Brechin 400/275 kV: 1,320 MW waiting
- Glendye Wind Farm: 167 MW waiting
- Lunanhead 2: 50 MW waiting
- Lunanhead: 34 MW waiting