Fiddes: grid connection queue

Fiddes GSP · SSEN Transmission (northern Scotland) · register of 26 November 2026

2 projects with 80 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2028 to 31 Oct 2031.

2projects in the queue
80 MWwaiting to connect
32 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
30 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Fiddes Battery StorageFIDDES BATTERY LIMITEDBattery storage3031 Oct 2028High31 Oct 2030Scopingnone
Meetlaw BESSCARRAVINDOON LIMITEDBattery storage5031 Oct 2031Medium31 Oct 2031Consents Approvednone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Fiddes GSPSSEN Distribution7.8 km
Laurencekirk PrimarySSEN Distribution8.1 km0 MW0 MW
Fetteresso GSPSSEN Distribution8.9 km
Inverbervie PrimarySSEN Distribution9.7 km0 MW0 MW
St Cyrus PrimarySSEN Distribution12.7 km0 MW4.9 MW
Stonehaven PrimarySSEN Distribution13.5 km0 MW0 MW

Thinking of connecting near Fiddes?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.