Creag Riabhach 132/33kV: grid connection queue
Creag Riabhach 132/33kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 13 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 31 Jul 2027 to 31 Jul 2027.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Creag Riabhach Wind Farm | CREAG RIABHACH WIND FARM LTD | Onshore wind | 13 | 31 Jul 2027 | High | 27 Sep 2029 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Overscaig Primary | SSEN Distribution | 13.2 km | 0 MW | 0.2 MW |
| Cassley GSP | SSEN Distribution | 13.3 km |
Thinking of connecting near Creag Riabhach 132/33kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Chleansaid Wind Farm 132kV: 96 MW waiting
- Dalchork 132kV: 200 MW waiting
- New Dalchork 132kV: 158 MW waiting
- Lairg: 135 MW waiting
- Coille Linne 132kV: 113 MW waiting