Coille Linne 132kV: grid connection queue

Coille Linne 132kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 113 MW is waiting to connect here (largest by capacity: onshore wind + storage). Contracted dates run from 31 Oct 2037 to 31 Oct 2037.

1project in the queue
113 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Coille LinneENERGYFARM UK COILLE LINNE LTDOnshore wind + storage11331 Oct 2037Low31 Oct 2037Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Lairg GSPSSEN Distribution0.8 km
Lairg PrimarySSEN Distribution0.8 km0 MW1.6 MW
Conon Falls PrimarySSEN Distribution9.0 km0 MW0 MW
Shin GSPSSEN Distribution9.0 km
Shin PrimarySSEN Distribution9.0 km0 MW2.5 MW
Tressady PrimarySSEN Distribution12.4 km0 MW0.2 MW

Thinking of connecting near Coille Linne 132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points