Dalchork 132kV: grid connection queue
Dalchork 132kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 200 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2032 to 31 Oct 2032.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Dalchork Farm | QAIR RENEWABLES UK LIMITED | Battery storage | 200 | 31 Oct 2032 | Low | 31 Oct 2032 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Lairg GSP | SSEN Distribution | 3.8 km | ||
| Lairg Primary | SSEN Distribution | 3.8 km | 0 MW | 1.6 MW |
| Conon Falls Primary | SSEN Distribution | 13.1 km | 0 MW | 0 MW |
| Shin GSP | SSEN Distribution | 13.1 km | ||
| Shin Primary | SSEN Distribution | 13.1 km | 0 MW | 2.5 MW |
| Tressady Primary | SSEN Distribution | 14.9 km | 0 MW | 0.2 MW |
Thinking of connecting near Dalchork 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- New Dalchork 132kV: 158 MW waiting
- Lairg: 135 MW waiting
- Coille Linne 132kV: 113 MW waiting
- Chleansaid Wind Farm 132kV: 96 MW waiting
- ACHANY EXTENSION WIND FARM 132/33KV: 81 MW waiting