ACHANY EXTENSION WIND FARM 132/33KV: grid connection queue

ACHANY EXTENSION WIND FARM 132/33KV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 81 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 26 Mar 2029 to 26 Mar 2029.

1project in the queue
81 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
81 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Achany Extension Wind FarmSSE GENERATION LIMITEDOnshore wind8126 Mar 2029High10 Feb 2031Awaiting Consents1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Lairg GSPSSEN Distribution12.1 km
Lairg PrimarySSEN Distribution12.1 km0 MW1.6 MW
Shin GSPSSEN Distribution13.4 km
Shin PrimarySSEN Distribution13.4 km0 MW2.5 MW
Conon Falls PrimarySSEN Distribution13.4 km0 MW0 MW
Gledfield PrimarySSEN Distribution19.3 km0 MW1.7 MW

Thinking of connecting near ACHANY EXTENSION WIND FARM 132/33KV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points