Wearside Connection Node B2 400kV substation: grid connection queue
Wearside Connection Node B2 400kV substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 200 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Oct 2035 to 30 Oct 2035.
1project in the queue
200 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Offerton 200MW BESS | Decerna Limited | Battery storage | 200 | 30 Oct 2035 | Low | 30 Oct 2035 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Wearside Connection Node B2 400kV substation?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Wearside Connection Node B 400kV: 1,797 MW waiting
- Wearside Connection Node B 2 400kV: 440 MW waiting
- Wearside Connection Node C 400kV: 249 MW waiting
- Stella West 400kV: 350 MW waiting
- Wearside Connection Node A 275kV: 1,100 MW waiting