Wearside Connection Node B 2 400kV: grid connection queue
Wearside Connection Node B 2 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 440 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 30 Oct 2035 to 30 Oct 2039.
2projects in the queue
440 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Lightsource Offerton | Lightsource Renewable UK Development Limited | Solar + storage | 240 | 30 Oct 2035 | Low | 30 Oct 2035 | Scoping | 1 |
| Hylton Bridge - Sunderland | SSE ENTERPRISE LIMITED | Battery storage | 200 | 30 Oct 2039 | Low | 30 Oct 2039 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Wearside Connection Node B 2 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Hawthorn Pit 400kV: 3,831 MW waiting
- Hawthorn Pit: 150 MW waiting
- Wearside Connection Node C 400kV: 249 MW waiting
- Wearside Connection Node D 400kV: 1,300 MW waiting
- Wearside Connection Node B2 400kV substation: 200 MW waiting