Wearside Connection Node D 400kV: grid connection queue
Wearside Connection Node D 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
4 projects with 1,300 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Oct 2035 to 30 Oct 2035.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Spennymoor BESS Station | IGP INTERNATIONAL PROSPECTING LIMITED | Battery storage | 400 | 30 Oct 2035 | Low | 30 Oct 2035 | Scoping | 1 |
| Overton Grange BESS | ANESCO LIMITED | Battery storage | 300 | 30 Oct 2035 | Low | 30 Oct 2035 | Scoping | 1 |
| Redhall BESS | ANESCO LIMITED | Battery storage | 300 | 30 Oct 2035 | Low | 30 Oct 2035 | Scoping | 1 |
| Zenobe Spennymoor BESS | ZENOBE ENERGY LIMITED | Battery storage | 300 | 30 Oct 2035 | Low | 30 Oct 2035 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 13 Oct 2026 | Zenobe Spennymoor BESS | 30 Oct 2034 | 30 Oct 2035 | +12 months |
Thinking of connecting near Wearside Connection Node D 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Hawthorn Pit 400kV: 3,831 MW waiting
- Hawthorn Pit: 150 MW waiting
- Wearside Connection Node C 400kV: 249 MW waiting
- Wearside Connection Node B 2 400kV: 440 MW waiting
- Hartmoor: 240 MW waiting