Wearside Connection Node D 400kV: grid connection queue

Wearside Connection Node D 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

4 projects with 1,300 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Oct 2035 to 30 Oct 2035.

4projects in the queue
1,300 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
1date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Spennymoor BESS StationIGP INTERNATIONAL PROSPECTING LIMITEDBattery storage40030 Oct 2035Low30 Oct 2035Scoping1
Overton Grange BESSANESCO LIMITEDBattery storage30030 Oct 2035Low30 Oct 2035Scoping1
Redhall BESSANESCO LIMITEDBattery storage30030 Oct 2035Low30 Oct 2035Scoping1
Zenobe Spennymoor BESSZENOBE ENERGY LIMITEDBattery storage30030 Oct 2035Low30 Oct 2035Scoping1

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
13 Oct 2026Zenobe Spennymoor BESS30 Oct 203430 Oct 2035+12 months

Thinking of connecting near Wearside Connection Node D 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points