Hawthorn Pit 400kV: grid connection queue

Hawthorn Pit 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

5 projects with 3,831 MW are waiting to connect here (largest by capacity: offshore wind, solar + storage). Contracted dates run from 31 Oct 2031 to 30 Jun 2034.

5projects in the queue
3,831 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Morven A Offshore Wind Farm (Prev Phoenix 1A)Morven Offshore Wind LimitedOffshore wind1,50031 Oct 2031Medium31 Oct 2031Scopingnone
Icewind Hawthorn PitKARI ENERGY LIMITEDOffshore wind1,00031 Oct 2031Medium31 Oct 2031Scoping1
Hawthorn Pit Green Energy CentreHAWTHORN PIT NG LIMITEDSolar + storage1,02531 Oct 2032Low31 Oct 2032Awaiting Consentsnone
Isenau EightIsenau Energy Storage Resources Eight LimitedBattery storage24931 Oct 2033Low31 Oct 2033Scoping1
ER HTP EnergyER PROJECT DEVELOPMENT CO LIMITEDSolar + storage5730 Jun 2034Low30 Jun 2034Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Thinking of connecting near Hawthorn Pit 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points