Wearside Connection Node B 400kV: grid connection queue

Wearside Connection Node B 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

5 projects with 1,797 MW are waiting to connect here (largest by capacity: battery storage, solar + storage). Contracted dates run from 30 Oct 2035 to 30 Oct 2035.

5projects in the queue
1,797 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
2date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
NatPower Hawthorn Pit Green Energy ParkNP SPV 29 LIMITEDBattery storage1,00030 Oct 2035Low30 Oct 2035Scoping1
Zenobe Hawthorn Pit BESSZENOBE ENERGY LIMITEDBattery storage30030 Oct 2035Low30 Oct 2035Scoping1
Lightsource Hawthorne PitLightsource Renewable UK Development LimitedSolar + storage24030 Oct 2035Low30 Oct 2035Scoping1
Hawthorn BESSREWE 8 LIMITEDBattery storage20030 Oct 2035Low30 Oct 2035Awaiting Consents1
Noventum Hawthorn PitNOVENTUM POWER SOLAR 2 LIMITEDSolar + storage5730 Oct 2035Low30 Oct 2035Scoping1

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 1 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
13 Oct 2026Hawthorn BESS31 Oct 203330 Oct 2035+24 months
13 Oct 2026Zenobe Hawthorn Pit BESS31 Oct 203730 Oct 2035-24 months

Thinking of connecting near Wearside Connection Node B 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.