Minety 400kV: grid connection queue
Minety 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
9 projects with 428 MW are waiting to connect here (largest by capacity: battery storage, solar + storage). Contracted dates run from 31 Oct 2024 to 30 Nov 2028.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Minety | HB411MIN Limited | Battery storage | 48 | 31 Oct 2024 | n/a | Consents Approved | none | |
| Fairholme BESS | HB411MIN Limited | Battery storage | 48 | 28 Feb 2025 | n/a | Consents Approved | none | |
| Pond Hill Farm 1 | PD688IRO LTD | Battery storage | 48 | 30 Apr 2025 | n/a | Consents Approved | none | |
| Pond Hill Farm 2 BESS | PD688IRO LTD | Battery storage | 48 | 31 May 2025 | n/a | Consents Approved | none | |
| Somerford | PD688IRO LTD | Solar + storage | 48 | 30 Jun 2025 | n/a | Consents Approved | none | |
| Southfields | PD688IRO LTD | Solar + storage | 48 | 30 Jun 2025 | n/a | Awaiting Consents | none | |
| Dog Trap Lane | HB411MIN Limited | Battery storage | 48 | 31 Oct 2028 | High | 31 Oct 2030 | Consents Approved | none |
| Southfields Farm | PD688IRO LTD | Battery storage | 48 | 31 Oct 2028 | High | 31 Oct 2030 | Consents Approved | none |
| JBM Solar -Minety | JBM SOLAR PROJECTS 14 LTD | Solar + storage | 48 | 30 Nov 2028 | Medium | 30 Nov 2028 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Fairford Primary | SSEN Distribution | 3.0 km | 0 MW | 5.7 MW |
| Cricklade Primary | SSEN Distribution | 6.4 km | 0 MW | 4.7 MW |
| Stanton Fitzwarren Primary | SSEN Distribution | 7.4 km | 0 MW | 1.9 MW |
| Lechlade Primary | SSEN Distribution | 8.4 km | 0 MW | 1.9 MW |
| Stratton Primary | SSEN Distribution | 9.1 km | 0 MW | 1.4 MW |
| Stratton (Main) BSP | SSEN Distribution | 9.2 km | 0 MW | 58 MW |
Thinking of connecting near Minety 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Patford Bridge 400kV: 250 MW waiting
- Farmoor 400kV: 840 MW waiting
- Botley West 400kV: 1,280 MW waiting
- Botley 400kV: 800 MW waiting
- Cowley 400kV: 1,157 MW waiting