Patford Bridge 400kV: grid connection queue
Patford Bridge 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 250 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 30 Oct 2033 to 30 Oct 2033.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Patford Bridge PV & BESS | NORTHAMPTON ENERGY PARK LIMITED | Solar + storage | 250 | 30 Oct 2033 | Low | 30 Oct 2033 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Calne Primary | SSEN Distribution | 1.8 km | 0 MW | 0 MW |
| Bromham Primary | SSEN Distribution | 5.0 km | 0 MW | 0 MW |
| Chippenham BSP | SSEN Distribution | 7.8 km | 0 MW | 0 MW |
| Cocklebury Primary | SSEN Distribution | 7.8 km | 0 MW | 0 MW |
| Rowden Primary | SSEN Distribution | 9.1 km | 0 MW | 0 MW |
| Lyneham Primary | SSEN Distribution | 9.6 km | 0 MW | 0 MW |
Thinking of connecting near Patford Bridge 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Melksham 400kV: 1,922 MW waiting
- Melksham B 400kV: 200 MW waiting
- Melksham B 132KV: 150 MW waiting
- Minety 400kV: 428 MW waiting
- Iron Acton 275kV: 120 MW waiting