Melksham B 132KV: grid connection queue
Melksham B 132KV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 150 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 15 Sep 2037 to 15 Sep 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Norrington Gate | ADV 004 LIMITED | Battery storage | 150 | 15 Sep 2037 | Low | 15 Sep 2037 | Consents Approved | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Devizes Primary | SSEN Distribution | 0.6 km | 0 MW | 0 MW |
| Easterton Primary | SSEN Distribution | 5.8 km | 0 MW | 0 MW |
| Bromham Primary | SSEN Distribution | 5.8 km | 0 MW | 0 MW |
| Melksham Town Primary | SSEN Distribution | 10.8 km | 0 MW | 0 MW |
| Melksham GSP | SSEN Distribution | 12.0 km | ||
| Calne Primary | SSEN Distribution | 12.1 km | 0 MW | 0 MW |
Thinking of connecting near Melksham B 132KV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Melksham 400kV: 1,922 MW waiting
- Melksham B 400kV: 200 MW waiting
- Patford Bridge 400kV: 250 MW waiting
- Shaftesbury 132kV: 100 MW waiting
- Minety 400kV: 428 MW waiting