Melksham 400kV: grid connection queue
Melksham 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
6 projects with 1,922 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 17 Jul 2026 to 31 Oct 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| JBM Solar 13 - Melksham | JBM SOLAR PROJECTS 13 LIMITED | Solar + storage | 50 | 17 Jul 2026 | n/a | Scoping | none | |
| Melksham (Tertiary) | MELKSHAM CALNE GREEN LIMITED | Solar + storage | 57 | 31 Dec 2026 | High | 30 Dec 2028 | Under Construction/Commissioning | 2 |
| Melksham | LIME DOWN SOLAR PARK LIMITED | Solar + storage | 500 | 31 Jul 2030 | Medium | 31 Jul 2030 | Awaiting Consents | none |
| South Brook | JBM Solar Limited | Solar + storage | 36 | 28 Jun 2037 | Low | 28 Jun 2037 | Awaiting Consents | none |
| Melksham BESS & PV | ELEMENTS GREEN LIMITED | Solar + storage | 800 | 15 Oct 2037 | Low | 15 Oct 2037 | Scoping | none |
| Melkshem (Cartridge Farm) | Queequeg Renewables Ltd | Battery storage | 480 | 31 Oct 2037 | Low | 31 Oct 2037 | Awaiting Consents | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Devizes Primary | SSEN Distribution | 0.6 km | 0 MW | 0 MW |
| Easterton Primary | SSEN Distribution | 5.8 km | 0 MW | 0 MW |
| Bromham Primary | SSEN Distribution | 5.8 km | 0 MW | 0 MW |
| Melksham Town Primary | SSEN Distribution | 10.8 km | 0 MW | 0 MW |
| Melksham GSP | SSEN Distribution | 12.0 km | ||
| Calne Primary | SSEN Distribution | 12.1 km | 0 MW | 0 MW |
Thinking of connecting near Melksham 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Melksham B 400kV: 200 MW waiting
- Melksham B 132KV: 150 MW waiting
- Patford Bridge 400kV: 250 MW waiting
- Shaftesbury 132kV: 100 MW waiting
- Minety 400kV: 428 MW waiting