Heastabhal Wind Farm Substation 132 KV: grid connection queue
Heastabhal Wind Farm Substation 132 KV · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 66 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 31 Oct 2033 to 31 Oct 2033.
1project in the queue
66 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Heastabhal Wind Farm | RWE Renewables UK Onshore Wind Limited | Onshore wind | 66 | 31 Oct 2033 | Low | 31 Oct 2033 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Heastabhal Wind Farm Substation 132 KV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.