ALCEMI SCORE BATTERY ENERGY STORAGE FACILITY 400KV SUBSTATION: grid connection queue
ALCEMI SCORE BATTERY ENERGY STORAGE FACILITY 400KV SUBSTATION · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 500 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Mar 2031 to 31 Mar 2031.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Alcemi Score Battery Energy Storage Facility | ALCEMI STORAGE DEVELOPMENTS 5 LIMITED | Battery storage | 500 | 31 Mar 2031 | Medium | 31 Mar 2031 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 13 Oct 2026 | Alcemi Score Battery Energy Storage Facility | 31 Oct 2029 | 31 Mar 2031 | +17 months |
Thinking of connecting near ALCEMI SCORE BATTERY ENERGY STORAGE FACILITY 400KV SUBSTATION?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.