ALCEMI SCORE BATTERY ENERGY STORAGE FACILITY 400KV SUBSTATION: grid connection queue

ALCEMI SCORE BATTERY ENERGY STORAGE FACILITY 400KV SUBSTATION · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 500 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Mar 2031 to 31 Mar 2031.

1project in the queue
500 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
1date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Alcemi Score Battery Energy Storage FacilityALCEMI STORAGE DEVELOPMENTS 5 LIMITEDBattery storage50031 Mar 2031Medium31 Mar 2031Scoping1

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
13 Oct 2026Alcemi Score Battery Energy Storage Facility31 Oct 202931 Mar 2031+17 months

Thinking of connecting near ALCEMI SCORE BATTERY ENERGY STORAGE FACILITY 400KV SUBSTATION?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report