Warwickshire Connection Node D 132kV: grid connection queue
Warwickshire Connection Node D 132kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 200 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Oct 2037 to 30 Oct 2037.
1project in the queue
200 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Tyler Hill Ansty | FRV Tyler Hill BESS 1 Ltd | Battery storage | 200 | 30 Oct 2037 | Low | 30 Oct 2037 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Warwickshire Connection Node D 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Warwickshire Connection Node A 400kV: 1,100 MW waiting
- Warwickshire Connection Node B 132kV: 100 MW waiting
- Berkswell 275kV: 257 MW waiting
- Berkswell B 275kV: 250 MW waiting
- Berkswell: 92 MW waiting