Berkswell 275kV: grid connection queue
Berkswell 275kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 257 MW are waiting to connect here (largest by capacity: battery storage, solar + storage). Contracted dates run from 31 Oct 2027 to 30 May 2028.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Berkswell Energy Storage | BERKSWELL BATTERY STORAGE LIMITED | Battery storage | 200 | 31 Oct 2027 | High | 30 Oct 2029 | Under Construction/Commissioning | 2 |
| Berkswell (Tertiary) | ENSO GREEN HOLDINGS P LIMITED | Solar + storage | 57 | 30 May 2028 | High | 30 May 2030 | Consents Approved | none |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 28 Jul 2026 | Berkswell Energy Storage | 30 Apr 2027 | 31 Oct 2027 | +6 months |
Thinking of connecting near Berkswell 275kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Berkswell B 275kV: 250 MW waiting
- Berkswell: 92 MW waiting
- Warwickshire Connection Node F 400kV: 249 MW waiting
- Warwickshire Connection Node A 400kV: 1,100 MW waiting
- Warwickshire Connection Node B 132kV: 100 MW waiting