Berkswell 275kV: grid connection queue

Berkswell 275kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

2 projects with 257 MW are waiting to connect here (largest by capacity: battery storage, solar + storage). Contracted dates run from 31 Oct 2027 to 30 May 2028.

2projects in the queue
257 MWwaiting to connect
0 MWalready connected
200 MWholding Gate 2
1date moves since 2 Jun 2026
257 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Berkswell Energy StorageBERKSWELL BATTERY STORAGE LIMITEDBattery storage20031 Oct 2027High30 Oct 2029Under Construction/Commissioning2
Berkswell (Tertiary)ENSO GREEN HOLDINGS P LIMITEDSolar + storage5730 May 2028High30 May 2030Consents Approvednone

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
28 Jul 2026Berkswell Energy Storage30 Apr 202731 Oct 2027+6 months

Thinking of connecting near Berkswell 275kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points