Harker 132kV: grid connection queue
Harker 132kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 30 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2037 to 31 Oct 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Barrow | NEW ENERGY PARTNERSHIP LIMITED | Battery storage | 30 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Bulk supply point 609621_132/11KV - No Heatmap Values | Electricity North West | 15.1 km | ||
| Primary substation 609621_132/11KV | Electricity North West | 15.1 km | 1.7 MW | 5.8 MW |
| Primary substation 609613 | Electricity North West | 17.4 km | 3.1 MW | 0.8 MW |
| Primary substation 609610 | Electricity North West | 18.8 km | 3.2 MW | 1 MW |
Thinking of connecting near Harker 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Harker 400kV: 1,832 MW waiting
- Harker: 150 MW waiting
- Harker 400/132KV: 57 MW waiting
- Stella South: 78 MW waiting
- Appin Wind Farm 132kV: 66 MW waiting