Harker 400/132KV: grid connection queue

Harker 400/132KV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 57 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 31 Oct 2029 to 31 Oct 2029.

1project in the queue
57 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Pivot Power Harker HybridPIVOTED POWER LLPSolar + storage5731 Oct 2029Medium31 Oct 2029Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Bulk supply point 609621_132/11KV - No Heatmap ValuesElectricity North West15.1 km
Primary substation 609621_132/11KVElectricity North West15.1 km1.7 MW5.8 MW
Primary substation 609613Electricity North West17.4 km3.1 MW0.8 MW
Primary substation 609610Electricity North West18.8 km3.2 MW1 MW

Thinking of connecting near Harker 400/132KV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points