Harker 400kV: grid connection queue
Harker 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
6 projects with 1,832 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 30 Oct 2028 to 31 Oct 2039.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Harker Green Energy Centre | Blackdyke BESS Limited | Solar + storage | 400 | 30 Oct 2028 | High | 30 Oct 2030 | Awaiting Consents | none |
| BESS Harker | REWE 4 LIMITED | Battery storage | 200 | 30 May 2031 | Medium | 30 May 2031 | Consents Approved | none |
| Harker PV & BESS Sub | HARKER ENERGY PARK LIMITED | Solar + storage | 250 | 1 Nov 2037 | Low | 1 Nov 2037 | Scoping | 1 |
| Low Harker BESS | Energi Generation 14 Ltd | Solar + storage | 400 | 30 Nov 2037 | Low | 30 Nov 2037 | Scoping | none |
| NEL Story | STORY ENERGY LIMITED | Battery storage | 240 | 30 Nov 2037 | Low | 30 Nov 2037 | Scoping | 1 |
| ESB Harker BESS | ESB (HARKER) LTD | Battery storage | 342 | 31 Oct 2039 | Low | 31 Oct 2039 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Bulk supply point 609621_132/11KV - No Heatmap Values | Electricity North West | 15.1 km | ||
| Primary substation 609621_132/11KV | Electricity North West | 15.1 km | 1.7 MW | 5.8 MW |
| Primary substation 609613 | Electricity North West | 17.4 km | 3.1 MW | 0.8 MW |
| Primary substation 609610 | Electricity North West | 18.8 km | 3.2 MW | 1 MW |
Thinking of connecting near Harker 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Harker: 150 MW waiting
- Harker 400/132KV: 57 MW waiting
- Harker 132kV: 30 MW waiting
- Stella South: 78 MW waiting
- Appin Wind Farm 132kV: 66 MW waiting