Stella South: grid connection queue
Stella South GSP · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 78 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Nov 2026 to 30 Nov 2026.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Stella Battery Energy Storage | CAPELLA BESS LTD | Battery storage | 78 | 30 Nov 2026 | High | 29 Nov 2028 | Consents Approved | 2 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 13 Oct 2026 | Stella Battery Energy Storage | 27 Sep 2025 | 30 Nov 2026 | +14 months |
Thinking of connecting near Stella South?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Stella West 400kV: 350 MW waiting
- Wearside Connection Node B 400kV: 1,797 MW waiting
- Wearside Connection Node B2 400kV substation: 200 MW waiting
- Harker 400kV: 1,832 MW waiting
- Harker: 150 MW waiting