Norton East 400kV: grid connection queue

Norton East 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

5 projects with 1,630 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 31 Oct 2031 to 30 Oct 2035.

5projects in the queue
1,630 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Zenobe NortonZENOBE ENERGY LIMITEDBattery storage15031 Oct 2031Medium31 Oct 2031Awaiting Consents1
NortonENSO GREEN HOLDINGS X LIMITEDSolar + storage40031 Oct 2032Low31 Oct 2032Scoping1
Letch Beck Energy ParkRenewable Energy Systems LimitedSolar + storage60031 Oct 2033Low31 Oct 2033Scoping1
Grindon GrangeSTARLIGHT ENERGY UK LIMITEDSolar + storage24030 Oct 2035Low30 Oct 2035Scopingnone
Lightsource Norton East PVLightsource Renewable UK Development LimitedSolar + storage24030 Oct 2035Low30 Oct 2035Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Thinking of connecting near Norton East 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points