Norton East 400kV: grid connection queue
Norton East 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
5 projects with 1,630 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 31 Oct 2031 to 30 Oct 2035.
5projects in the queue
1,630 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Zenobe Norton | ZENOBE ENERGY LIMITED | Battery storage | 150 | 31 Oct 2031 | Medium | 31 Oct 2031 | Awaiting Consents | 1 |
| Norton | ENSO GREEN HOLDINGS X LIMITED | Solar + storage | 400 | 31 Oct 2032 | Low | 31 Oct 2032 | Scoping | 1 |
| Letch Beck Energy Park | Renewable Energy Systems Limited | Solar + storage | 600 | 31 Oct 2033 | Low | 31 Oct 2033 | Scoping | 1 |
| Grindon Grange | STARLIGHT ENERGY UK LIMITED | Solar + storage | 240 | 30 Oct 2035 | Low | 30 Oct 2035 | Scoping | none |
| Lightsource Norton East PV | Lightsource Renewable UK Development Limited | Solar + storage | 240 | 30 Oct 2035 | Low | 30 Oct 2035 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Norton East 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Norton: 280 MW waiting
- Norton 400kV: 275 MW waiting
- Norton 275kV: 98 MW waiting
- Teeside Connection Node A 400kV: 1,240 MW waiting
- Spennymoor 400kV: 850 MW waiting