Norton 400kV: grid connection queue
Norton 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 275 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2031 to 31 Oct 2031.
1project in the queue
275 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Al Boum Photo (Norton) | AL BOUM PHOTO LTD | Battery storage | 275 | 31 Oct 2031 | Medium | 31 Oct 2031 | Consents Approved | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Norton 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Norton East 400kV: 1,630 MW waiting
- Norton: 280 MW waiting
- Norton 275kV: 98 MW waiting
- Teeside Connection Node A 400kV: 1,240 MW waiting
- Spennymoor 400kV: 850 MW waiting