Benzene

Norton 400kV: grid connection queue

Norton 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 275 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2031 to 31 Oct 2031.

1project in the queue
275 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Al Boum Photo (Norton)AL BOUM PHOTO LTDBattery storage27531 Oct 2031Medium31 Oct 2031Consents Approvednone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Thinking of connecting near Norton 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points