Spennymoor 400kV: grid connection queue

Spennymoor 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

4 projects with 850 MW are waiting to connect here (largest by capacity: demand or network only, solar + storage). Contracted dates run from 1 Oct 2028 to 30 Oct 2035.

4projects in the queue
850 MWwaiting to connect
0 MWalready connected
500 MWholding Gate 2
0date moves since 2 Jun 2026
550 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Spennymoor Greener Grid ParkSpennymoor Grid Solutions LimitedDemand or network only5001 Oct 2028High16 May 2031Consents Approved2
SpennymoorPIVOTED POWER LLPBattery storage5031 Oct 2028High31 Oct 2030Awaiting Consents1
Spennymoor PV & BESSCSE27 LIMITEDSolar + storage5030 Jul 2032Low30 Jul 2032Scopingnone
Spennymoor PV & BESS SubO&G Solar (SPV 20) LimitedSolar + storage25030 Oct 2035Low30 Oct 2035Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Thinking of connecting near Spennymoor 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.