Spennymoor 400kV: grid connection queue
Spennymoor 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
4 projects with 850 MW are waiting to connect here (largest by capacity: demand or network only, solar + storage). Contracted dates run from 1 Oct 2028 to 30 Oct 2035.
4projects in the queue
850 MWwaiting to connect
0 MWalready connected
500 MWholding Gate 2
0date moves since 2 Jun 2026
550 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Spennymoor Greener Grid Park | Spennymoor Grid Solutions Limited | Demand or network only | 500 | 1 Oct 2028 | High | 16 May 2031 | Consents Approved | 2 |
| Spennymoor | PIVOTED POWER LLP | Battery storage | 50 | 31 Oct 2028 | High | 31 Oct 2030 | Awaiting Consents | 1 |
| Spennymoor PV & BESS | CSE27 LIMITED | Solar + storage | 50 | 30 Jul 2032 | Low | 30 Jul 2032 | Scoping | none |
| Spennymoor PV & BESS Sub | O&G Solar (SPV 20) Limited | Solar + storage | 250 | 30 Oct 2035 | Low | 30 Oct 2035 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Spennymoor 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Wearside Connection Node B2 400kV substation: 200 MW waiting
- Wearside Connection Node B 2 400kV: 440 MW waiting
- Wearside Connection Node B 400kV: 1,797 MW waiting
- Norton East 400kV: 1,630 MW waiting
- Norton: 280 MW waiting